Leighton Contractors and ARTC in Alliance to deliver Southern Sydney Freight Line
Leighton Contractors has been selected by Australian Rail Track Corporation (ARTC) to deliver the final stage of the Southern Sydney Freight Line (SSFL) in an Alliance contract worth $150 million for Leighton Contractors. The Alliance will complete the construction of a 36km dedicated freight line between Macarthur and Sefton in southern Sydney. The SSFL will provide a third track in the rail corridor specifically for freight services, allowing passenger and freight services to operate independently...
Southern Sydney Freight Line Back on Track
Construction work on the 36 kilometre SSFL will recommence almost immediately and the first section of track, between Leightonfield and Sefton, is scheduled to be laid between March and July next year, the Chief Executive of ARTC, David Marchant, said today