Construction Progress

The SSFL will be constructed under a number of discrete contracts. The contracts will be arranged on a work type and/or geographic extent. The key packages for construction comprise of the following activities:

  • Formation construction – earthworks and retaining walls
  • Bridges and major culverts
  • Construction at stations
  • Track construction
  • Signalling and communications

The entire construction program is expected to take approximately 18 months with significant overlap between the construction packages.

ARTC has engaged a Construction Management Team to manage and coordinate the activities of the various contractors.

Number Title Uploaded
001 Construction Programme Update 09 Dec 2008
002 Bankstown LGA Programme – 4 week look ahead 11 Mar 2009
003 Campbelltown LGA Programme – 4 week look ahead 06 Feb 2009
004 Fairfield LGA Programme – 4 week look ahead 06 Feb 2009
005 Liverpool LGA Programme – 4 week look ahead 06 Feb 2009
Station Works
Number Title Uploaded
001 Cabramatta Station upgrade sign 26 Feb 2009
002 Casula Station upgrade sign 26 Feb 2009
003 Leumeah Station upgrade sign 26 Feb 2009
004 Minto Station upgrade sign 26 Feb 2009
005 Sefton Station upgrade sign 26 Feb 2009
006 Warwick Farm Station upgrade sign 26 Feb 2009
Arenco
Number Title Uploaded
001 Arenco Introduction & Progress 21 Oct 2008
002 Arenco Progress Report 01 02 Feb 2009
003 Arenco Progress Report 02 04 Mar 2009
Garter Rose
Number Title Uploaded
001 Gartner Rose Introduction 03 Dec 2008
002 Gartner Rose Progress Report 01 03 Dec 2008
003 Gartner Rose Progress Report 02 02 Feb 2009
004 Sefton Station Construction Update 09 Sep 2009
Reed
Number Title Uploaded
001 Reed Constructions Introduction 18 Feb 2009
002 Reed Constructions Monthly Status Report February 2009 01 Apr 2009
003 Reed Constructions Monthly Status Report March 2009 01 Apr 2009